Add a task dependency
Dependencies let you say that one task must happen in relation to another, helping you sequence work correctly.
- Open the task that depends on another.
- Add a dependency and choose the task it depends on. You can only pick another task in the same project.
- Choose the Dependency type: Finish to Start, Start to Start, Finish to Finish, or Start to Finish.
- Optionally set Lag days (a delay, which can be negative) and add Notes.
- Save the dependency.
Warning: The system prevents circular dependencies (where tasks end up depending on each other in a loop) and will not let you add the same dependency twice.
You can update a dependency’s type, lag, or notes later, or remove it entirely from the task.